The following facilities are created in the new permanent campus by reusing the dismantled materials of the kitchen shed in the old campus.

Green Up SPAV
Construction of Shed for DG sets:
This facility for DG sets is located in the 2.66 Acre site of SPAV beside the substation building with an area of 62 Sqm using the old dismantled Structural steel I-sections, purlins, trusses, circular pipes and Galvalume roofing sheets.
Reuse1
Construction of Shed for RO plant in the Institute block: This facility has been provided on the terrace of the Institute block for placing RO plants for drinking water purposes with an area of 35 Sqm using old dismantled material like MS circular tubes, trusses and Galvalume roofing sheets.Reuse2

Other facilities created by reusing the old materials : Stands for Water coolers (8nos) in the Institute block, Gabions for plants (4nos), Storages for onions and potatoes in the kitchen (2nos), Basket ball poles (2nos), key boxes using old Ply wood (3nos) are fabricated using old MS angular, Circular pipes and Mesh.
Reuse3  Reuse4  Reuse5

Providing Lighting facilities in the 2.66 Acre ground: Around 100 mts of electrical old wire is reused for providing lighting in the 2.66 Acre ground.
Details of Steel, wood and roofing materials Reused in the New Campus.
Reuse6  Reuse7  Reuse8

Green Up SPAV
Sl noMaterial ReusedQuantityFacility created
01MS I-sections, Circular pipes, square pipes, trusses, mesh.3000 KgsShed for DG shed, Shed for RO plant, gabions, cooler stands, storage units.
02Galvalume Roofing sheets200 SqmRoof for DG shed, Ro shed.
0318mm Ply wood and 4mm Veneer.5 SqmKey boxes
3000 Kgs Shed for DG shed, Shed for RO plant, gabions, cooler stands, storage units. 02 Galvalume Roofing sheets 200 Sqm Roof for DG shed, Ro shed. 13 18mm Ply wood and 4mm Veneer. 5 Sqm Key boxes